| (A) Construction Linked : |
| S.No |
Payment Due On |
% Age |
Other Applicable Charges |
| 1 |
Booking Amount |
2BHK+Study(6.50 Lacs), 3BHK+Study(8.00 Lacs) |
|
| 2 |
On or before 2 months of the Application |
20% of BSP (Less booking Amount*) |
IDC |
| 3 |
On or before 4 months of the Application |
10% of BSP |
|
| 4 |
On Start of Excavation |
10% of BSP |
|
| 5 |
On laying of upper basement slab |
10% of BSP |
|
| 6 |
On laying of 3rd floor Roof Slab |
7.5% of BSP |
Car Park Charges + IFMD |
| 7 |
On laying of 6th floor Roof Slab |
7.5% of BSP |
|
| 8 |
On laying of 9th floor Roof Slab |
6.5% of BSP |
|
| 9 |
On laying of 12th floor Roof Slab |
6.5% of BSP |
|
| 10 |
On laying of 16th floor Roof Slab |
6% of BSP |
Electric Sub Station Charges |
| 11 |
On laying of top floor Roof Slab |
6% of BSP |
PLC |
| 12 |
On Completion of internal plaster & flooring within the Apartment |
5% of BSP |
|
| 13 |
On Offer of Possession |
5% of BSP |
Social Club Membership + Maintenance Advance |
| |
Total |
100% |
|